Skip to content

US Global Leader in LNG Exports Capacity

Read Time: 3 mins

The United States has achieved the largest liquefied natural gas (LNG) export capacity and highest LNG exports of any country, according to the latest report from the US Energy Information Administration (EIA).

As of July 2022, the US has surpassed previous leaders Australia and Qatar in export capacity, and has exceeded any other country in LNG exports, with exports averaging 11.1 billion cubic feet per day (Bcf/d) during the first half of 2022.

The US became the global leader in LNG export capacity when the Calcasieu Pass LNG export terminal project placed all its liquefaction trains in service ahead of schedule. The trains were originally set to be in service by August.

Calcasieu Pass is a 1.3 billion Bcf/d liquefaction facility located in Cameron Parish, LA. The facility, which uses mid-scale liquefaction technology, started LNG production 30 months after its final investment decision — the shortest construction period for any US LNG export project so far.

In addition to 18 mid-scale liquefaction trains, Calcasieu Pass includes an onsite natural gas-fired plant to generate electricity for the facility’s operations – three pre-treatment trains, two LNG storage tanks (with a capacity of 4.4 Bcf each) and two shipping berths capable of loading LNG vessels with carrying capacities of up to 185,000 cubic meters (4 Bcf).

The terminal receives its feedgas through Venture Global’s 24-mile, 42-inch-diameter TransCameron Pipeline, which has interconnections with the ANR, TETCO, and Bridgeline pipelines.

US capacity expansion is far from finished. It is set to increase even further following completion of three additional projects.

The furthest along is Golden Pass LNG, which started construction in 2019. The project includes construction of three standard-size liquefaction trains with peak LNG production capacity of up to 0.8 Bcf/d per train, for a total capacity of 2.4 Bcf/d. The facility is on the site of an existing regasification facility and will use shared infrastructure, which helps to reduce project costs and shorten the construction timeline.

Two other projects under construction use a modular technology with mid-scale refrigeration trains, which has a shorter project construction timeline.

Plaquemines LNG will consist of 24 mid-scale trains, each with a peak capacity of 0.07 Bcf/d. Each liquefaction train is part of a two-unit block for a total of 12 blocks with a combined peak capacity of 1.8 Bcf/d, noted the EIA.

Corpus Christi Stage III will be built on the site of an existing terminal with three liquefaction trains in operation. Each of the 14 new, mid-scale trains under construction has a peak capacity of 0.11 Bcf/d, and is part of a two-unit block for a total of seven blocks with a combined peak capacity of 1.6 Bcf/d.

Once completed, the three export projects will expand US LNG peak export capacity by a combined 5.7 Bcf/d by 2025.

For more information visit www.eia.gov